Construction look ahead: 2023

Continuing Activity

Work continues on the following elements:

  • Ten food and retail vendor locations in the terminal building and in the rest of the project.
  • Entrance from Alaskan and Yesler ways (instead of staging at Pier 48) after removal of temporary lane on Alaskan Way.
  • New Marion Street Pedestrian Bridge over Alaskan Way.
  • Completion of street, sidewalk, and utility work in front of the entry building. When complete, a passenger pick-up and drop-off area and taxi parking will open.

Construction details

  • New entry building along Alaskan Way and elevated pedestrian connector leading to passenger building opened on August 3rd.
  • Colman Dock will remain open throughout construction.

Contact

Anticipated activities

  • Major activities summer and fall 2023 include: 
    • Completion of Alaskan Way S between S Main St and Yesler Way, including removal of the temporary ferry access lane from Pier 48 to Colman Dock following completion of Colman Dock project  
    • Beginning construction of connection between existing Alaskan Way north of Pine St, Elliott Way and the new Alaskan Way south of Pine St.  

Construction details

  • Work anticipated to be complete by late 2024. 
  • Work will be on Alaskan Way between S Main St and Yesler Way and between Pike and Pine streets. 
  • Pedestrian access will be maintained to all businesses and residences.  
  • Driveway access to all buildings will be maintained. 
  • Daytime work, typically 7 AM to 5 PM Monday through Friday. 
  • Expect construction equipment and vehicles moving in and out of the work zone.   
  • Construction trucks and equipment may be noisy.   

Contact

Anticipated activities

  • Work includes installing utilities, paving the pedestrian space, building the protected bike facility, landscaping and art installation. 

Construction details

  • Work will be from Summer 2022 to Late 2024. 
  • Work will be west of Alaskan Way between Yesler Way and Pike St. 
  • Pedestrian access will be maintained to all businesses and residences.  
  • Driveway access to all buildings will be maintained. 
  • Daytime work, typically 7 AM to 5 PM Monday through Friday. 
  • Expect construction equipment and vehicles moving in and out of the work zone.   
  • Construction trucks and equipment may be noisy.   

Contact

Anticipated activities

  • Constructing seismic improvements. 
  • Improvements to enhance access, safety, views and flexible use of the space. 
  • Work will occur at Pier 58 – between Pier 57 (Miner’s Landing + the Great Wheel) and Pier 59 (the Seattle Aquarium). 
  • Pile driving will resume in fall 2023. 

Construction details

  • Work will primarily be from the waterside with minimal impacts to people walking along the waterfront. 
  • Work hours are generally from 6:30 AM to 3 PM. 

Contact

Anticipated activities

  • Constructing a new, wider bridge to better connect the large volume of travelers who commute via ferry from Colman Dock to downtown. 
  • Work will occur on Marion St between Western Ave and Alaskan Way. 

Construction details

  • A temporary Marion Street Pedestrian Bridge is open until the permanent bridge is ready to open to the public, anticipated in fall 2023. 
  • Removal of the temporary bridge will be removed following the opening of the new bridge and is anticipated to wrap up by the end of 2023. 
  • Occasional nighttime closures of Marion St between Alaskan Way and Western Ave.  
  • Lane reductions on Alaskan Way during impactful work.  
  • Occasional weekend, overnight and early work. 
  • Sidewalk closures on east side of Alaskan Way between Columbia and Marion streets and on the south side of Marion St between Alaskan Way and Western Ave.  

Contact

Anticipated activities

  • The expansion includes a new building, the Ocean Pavilion; a west-end renovation of Pier 59; a renovation and expansion of Pier 60; and seamless connections to a greatly improved public waterfront. 

Construction details

  • The improvements started in 2020 and are anticipated to be complete by 2024. 
  • Regular work hours Monday through Friday from 7 AM to 5 PM.   
  • Alaskan Way between Pike and Pine streets is closed daily during work hours info the fall.  
  • Outside of work hours, there will be a single lane northbound between Pike and Pine streets located in the vicinity of the existing S-curves.  
  • There will be special accommodations when cruise ships are loading/unloading at Pier 66, follow posted signs.  
  • Pedestrian access maintained at all times on the west side of Alaskan Way 

Contact

Anticipated activities

  • Overlook Walk, located between the Seattle Aquarium and Pike Place Market, is a key connection between the waterfront and downtown and will become a focal point for the new waterfront. 

Construction details

  • Construction began in summer of 2022 and is anticipated to be completed in early 2025.  
  • Work areas are between Alaskan Way at Pike St and Elliott Way near Pine St. 
  • Typical work hours are 7 AM to 5 PM Monday through Friday, with work starting at 6 AM when needed and communicated to neighbors in advance. 
  • Pedestrian access below Overlook Walk will be maintained on the west side. 

Contact

Anticipated activities

  • Pike Pine Streetscape and Bicycle Improvements (a part of the Downtown Seattle Association’s Pike Pine Renaissance program) will provide a vibrant pedestrian experience on Pike and Pine streets between Capitol Hill and the Pike Place Market, with connections to the new waterfront.  

Construction details

  • Construction began in early 2023 and is anticipated to be complete in late 2024.  
  • Work areas are on Pike and Pine streets, from 1st Ave to Bellevue Ave. 
  • Access to all properties on both Pike and Pine streets, including businesses and residences, will be maintained during construction work. Detour signage will direct pedestrians, bicyclists and drivers when necessary.   
  • Work hours typically Monday through Friday, 7 AM to 5 PM.  
  • Weekend work is planned at intersections; details to be communicated in advance through the weekly construction emails.   

Contact

Anticipated activities

  • Constructing improvements on four east-west streets in the heart of Pioneer Square. The changes will prioritize pedestrians, improve sidewalks, and increase greenery.  

Construction details

  • Construction is expected to begin in late 2023 and take about a year to complete.  
  • Work areas are on S Washington, S Main, King and Yesler streets between 2nd Ave and Alaskan Way.  
  • Access to businesses and residences will be maintained at all times.  